image 17.12.2017
EET 10:02:37
CET 09:02:37
   
Click for latest actual time
 
 
 
 
 
 
 
 
 
 
 
 
 
Focus focus preview Click on focus to view     image SCC Latvia
    image SCC Lithuania
    image Estonian Swedish Chamber
    image Estonian Swedes
barometer The Estonian
Economic Barometer
    image Key Economic Indicators
    image Foreign Direct Investments
    image Goods Exports and Imports
    image Balance of Payments





picture News December, 17 2017
LEADELL Pilv Law Office: Do only builders run the risks of unforeseeable construction works? LEADELL Pilv Law Office: Do only builders run the risks of unforeseeable construction works?

Attorneys-at–law Britta Oltjer and Epp Lumiste wrote in the article in business newspaper Äripäev (published on 1 February 2017) that it is not always possible to avoid (court) disputes in construction procurements.

 

Even along with very carefully and thoroughly planned construction procurement, the fulfilment of concluded contract can lead to time-consuming and resource-intensive (court) dispute.   Unfortunately, one must admit that in the light of current Law on Public Procurement (LPP) and court practice, it is likely not possible to instantly avoid these situations to occur in future.

 

What causes disputes? Insufficient identification of supplier’s needs, lack of previous experience, unclearly formulated purchase inquiry, directed procurements, undersupply, lack of cooperation between contractor and tenderer, construction workload etc. Questions regarding workload not necessarily arise during planning phase of procurement, as well as subcontractors may not draw the attention to this issue before an offer made (during phase of assessing the object). The real volume of construction works or some drawbacks in submitted by contractor project can emerge after construction had already begun (for example situation with procurement of the university’s library). What are the subcontractor’s options in this case?

 

LPP and the court practice restrict the process of making amendments of contract, as well as subcontractors’ options to stop the construction. According to the court practice, the errors in project are not the ground for terminating the construction, particularly in those cases when errors can be apparently eliminated by parties’ agreement and good faith (see example of clarification by the court in the dispute between Skanska and Kiviõli secondary school). The Supreme Court clarified in 2016 the limitations of potential alternatives of subcontractors. Namely, one might claim the amendments of procurement contract only if this option is clearly provided in the contract. This means that if the contractor hasn’t foreseen the probability of amendments of the contract during initial process of coordination of the procurement, then subcontractor couldn’t demand making any amendments to existing contract because of increased workload.

 

As it follows from the case-law of the Court of Justice, it is not allowed to change the procurement contract by agreement in case of increased or decreased construction workload; instead there should be organized new procurement with adjusted conditions.

 

The alternatives of subcontractor and tenderer have limited options to act when inability to proceed with construction arise due to increased workload (and also decreased) during the process. Making amendments to procurement contract are allowed only in specific cases, thus in the court practice it is preferred to conduct a new procurement process in order to guarantee equal treatment to tenderers.

 

Long awaited LPP gives a bright hope  that requirement for making amendments of procurement contract will be alleviated, and both tenderer and subcontractor will have right to bring some adjustments to the contract during constructive cooperation, if any described above  problem occurs. Currently, this is still being processed by the Estonian Parliament, whereas the last proposals were submitted on January 18th, 2017.

 

LEADELL law offices are among the leading business law firms in the Baltic countries, providing services to business clients.



< back
royal members
sweden
swedishtrade
abb
maqs
meritonhotels
roedl
seb
ericsson
telia
hemtex
itk
Västerbottensost
ajtooted
Wendre
Pärnu Bay Golf
Saare Golf
Tartu Ülikool
VIA3L spedition
 
Swedish Chamber of Commerce in Estonia  ·  GSM: +372 501 9813  ·  e-mail: info[at]swedishchamber.ee  ·  statistics